Want to take a look at everything we've done?
View All Our MissionsWe provide both test and fuelling services at the launch site. We arrive, set up our equipment and perform the final checks on the spacecraft propulsion system prior to fuelling operations. This involves:
We have designed ground support equipment that will allow us to fuel and pressurise multiple spacecraft simultaneously – something we did for the Formosat-7 launch campaign. A typical launch campaign timeline for a singular monopropellant spacecraft is shown below:
| DAY | ACTIVITY | SUPPORT REQUIRED |
|---|---|---|
|
1
|
Fly to CSG | |
|
2
|
Security Processing of Team at CSG and Location of Equipment. Start unpacking and setup of GSE | CSG Security support for badging of personnel and movement of equipment |
|
3
|
Start Set up and check out of FGSE | Supply of required test gases and gas adapter interfaces by CSG if required. |
|
4
|
Continue set up and check out of FGSE. SCAPE training | Access to fuel storage area required. SCAPE fitting / training provided CSG |
|
5
|
TRR for spacecraft pressure testing and movement of propellant tanks to loading area | CSG to support with moving of propellant tanks. |
|
6
|
Spacecraft pressure and leak checks | Gases provided by CSG. Safety controlled by CSG (restricted access during pressurisation etc). Customer to monitor spacecraft as required. |
|
7
|
Spacecraft pressure and leak checks | As above. |
|
8
|
Contingency day for spacecraft leakage/pressure checks. TRB for MEOP testing. | As above. |
|
9
|
Rest Day | |
|
10
|
Finalisation of FGSE setup including connection to Transfer Tank and spacecraft. TRR for fuelling activities. | CSG safety to support TRR meeting. |
|
11
|
Fuelling Day. Includes the fuelling and pressurisation of spacecraft and set-down of FGSE ready for decontamination. Finalisation of spacecraft wirelocking. | CSG safety to support fuelling activities. |
|
12
|
Fuelling contingency day. Start of decontamination activities and fuelling TRB. | Customer/EAL/CSG present at TRB. CSG safety supporting decontamination. |
|
13/14
|
Rest Day | |
|
15
|
Continue decontamination activites. | CSG safety supporting decontamination. |
|
16
|
Continue decontamination activites. | As above. |
|
17
|
Complete Decontamination. Start packing of FGSE. | CSG arranging transportation of FGSE to storage for next campaign. |
|
18
|
Fly back to UK |